Implementing the Oregon Energy Strategy

Proposed Framework for Strategic Transmission Siting

EO 25-29 calls on the Oregon Department of Energy, in coordination with the Oregon Public Utility Commission and the Governor’s Office, to undertake a process to evaluate and propose a framework to strategically accelerate:

  1. Identification and designation of transmission corridors, including on public lands (state and federal);

  2. Streamlined partial siting and permitting approvals for future projects in those corridors or within existing transmission rights-of-way; and

  3. Targeting direct financial support for projects that are determined to benefit the public interest.

Proposed Framework for Strategic Transmission Siting 

Element #1 - Identification and designation of strategic transmission priorities

Key gaps/needs:

  • Prioritization of transmission projects.

  • Principles and criteria to identify strategic transmission priorities.

Enabling actions:

  • Establish dedicated state resource – within an existing agency or through creation of a new transmission entity – to identify state priorities.

  • Recognize WestTEC 10- and 20- year projects as state priorities and engage with utilities, large loads, and neighboring states to identify paths forward.

Element #2 - Streamlined siting and permitting

Key gaps/needs:

  • Expedite siting and permitting for priority projects to increase pace of development through assistance in navigating existing permitting frameworks.

  • Streamline siting and permitting to increase efficiency across all projects, while maintaining existing protections and sufficient opportunity for public comment.

  • Strengthen public engagement, starting early in the process.

Enabling actions for priority projects:

  • Projects identified as a priority are deemed to meet the need standard in the Energy Facility Siting Council’s process.

  • Establish dedicated state liaisons to accompany priority projects from start to finish and provide support through planning and permitting processes.

  • For priority projects, provide clear direction from the Governor’s Office and agency directors to focus on permitting these projects.

  • Extend EFSC’s jurisdiction to projects deemed priority projects to ensure consistency, focus state resources, and expedite permitting.

Enabling actions for all projects:

  • Increase qualified staff at agencies to meet increased demand for permits.

  • Fund increased staffing needs, including liaison positions, through developer contributions.

  • Establish EFSC standards specific to transmission lines.

  • Update Goal 13, Energy Conservation.

  • Make adjustments to state permitting processes to reduce redundancy and delays while maintaining sufficient opportunity for public comment. This includes cooperation between EFSC, ODOT, the OPUC, DLCD, other relevant state agencies, local governments, and state and federal processes.

  • Develop a framework for community benefits to inform projects.

  • Create an opt-in system for landowners in early outreach, with compensation.

  • Enable counties to defer transmission siting authority to EFSC.

  • Expand the “Green Corridor” rule to all counties.

Element #3 - Deploy targeted non-wires solutions at increased pace and scale

Key gap/need (non-wires alternatives):

  • Deploy targeted non-wires solutions at increased pace and scale, particularly in the very near term.

Enabling actions:

  • Establish a statewide network for peer learning and technical assistance in deploying non-wires solutions.

  • Continue to advance mechanisms through OPUC processes for investor-owned utilities to improve existing grid utilization.

  • Expand funding for energy efficiency and demand side flexibility by removing the cap on the public purpose charge contribution for large loads.

Element #4 - Catalyzing projects through financial support and procurement

Key gaps/needs:

  • Ensure that priority transmission lines can be built at the pace and scale needed to meet reliability, affordability, and state clean energy goals.

  • Mitigate ratepayer impacts of transmission development.

Enabling actions:

  • Address wildfire liability and accountability, building on report expected from the OPUC in fall 2026.

  • Direct an existing agency or state transmission entity to attract federal funding for transmission projects, including supporting Tribes, utilities, and counties in securing federal funding.

  • Enable state bonding authority to support low-cost transmission infrastructure development.

  • Establish the state as a transmission developer-of-last-resort, including the ability to issue competitive tenders to ensure needed transmission is built in a timely manner.