Implementing the Oregon Energy Strategy
Proposed Framework for Strategic Transmission Siting
EO 25-29 calls on the Oregon Department of Energy, in coordination with the Oregon Public Utility Commission and the Governor’s Office, to undertake a process to evaluate and propose a framework to strategically accelerate:
Identification and designation of transmission corridors, including on public lands (state and federal);
Streamlined partial siting and permitting approvals for future projects in those corridors or within existing transmission rights-of-way; and
Targeting direct financial support for projects that are determined to benefit the public interest.
-
ODOE, with assistance from the OPUC and in coordination with the Governor’s Office, researched perspectives on challenges to building transmission infrastructure in Oregon and studied approaches to prioritizing and building transmission infrastructure in other states. The proposed framework draws on lessons from Oregon and other states in identifying elements of a draft framework for strategic transmission siting in Oregon.
ODOE received technical assistance from the National Governors Association Policy Academy in undertaking research to inform this memo. This included convening an in-person workshop in May 2026, during which ODOE collected perspectives on challenges and potential solutions from investor- and consumer-owned utilities, the Bonneville Power Administration, private developers, Tribes, local governments, landowners, advocacy groups, and peer agencies. ODOE also issued a questionnaire in August 2026 to deepen understanding of the themes that emerged from the workshop and seek broader perspectives on key issues. Insights from that questionnaire have informed the final recommendations. In October 2026 ODOE will hold a final workshop, in cooperation with the NGA Policy Academy, to discuss the findings of this memo in the context of broader work underway to address the need for transmission expansion in Oregon.
-
Transmission infrastructure is critical for Oregonians’ personal well-being, economic prosperity, and climate and environmental protection. It delivers the electricity that powers our daily lives and enables businesses to grow and thrive. It also provides access to least-cost clean electricity across Oregon and the West, making it a critical component for achieving Oregon’s decarbonization objectives. For these reasons, expanding and modernizing the grid is an essential goal for Oregon.
At the same time, transmission poses challenges. Transmission lines and infrastructure can have negative impacts for specific local communities in contrast to the benefits for the larger system. As long, linear projects, transmission lines often cross a combination of Tribal reservations and ceded lands, private property, and protected state and federal lands and waters. While transmission lines may bring overall economic benefit, they can adversely affect important cultural and natural resources as well as home and property values where they are sited. Early and frequent meaningful engagement is important to ensure that negative effects are avoided wherever possible, minimized if not possible to avoid, and mitigated.
In the research conducted for this memo, five core values repeatedly surfaced that should be considered as the state pursues transmission acceleration: (1) affordability, (2) securing reliability, (3) preserving cultural resources, (4) protecting natural and working lands, and (5) fostering transparency and engagement.
-
Transmission infrastructure projects are large, capital-intensive, and complex. Several areas were identified that can contribute to long timelines to plan for, permit, and construct transmission infrastructure. We do not characterize these areas as good or bad, or as problems that need to be “solved.” Rather, these are complexities that need to be addressed when considering how to reduce the timelines for transmission development:
Long, linear projects cross multiple lands and waters, including under Tribal, private, state, and federal ownership, and often require long processes to undertake the required biological and anthropological studies, and to gain access.
Permitting processes are complex and involve multiple jurisdictions (Tribal, local, state, multi-state, federal) and timelines. Transmission lines can face multiple permitting and process layers that can lead to long timelines, including where processes run sequentially rather than concurrently. Varying appeal pathways for major decisions in permitting at the state and county levels and condemnation proceedings add legal complexity, draw out timelines, and add to the cost of transmission line permitting.
Projects that cross multiple states bring up additional difficult questions about cost allocation and involve increased complexity around siting and permitting.
Outreach to affected landowners and broader public engagement is essential to securing access to land and identifying least-conflict solutions to siting. This takes time. Opposition to a line can contribute to significant delays through lengthy appeals processes that ensure due process.
It takes time to secure financing for large transmission investments, and often multiple parties are involved in sponsoring a project. These are multifaceted interactions and transactions that require time to negotiate.
Utilities in Oregon and across most of the West are not part of a Regional Transmission Organization. This leads to fragmented approaches to transmission planning and investment, increasing complexity and timelines, creating inefficient solutions, and risking underbuilding necessary infrastructure.
Wildfire risk and liability is raising borrowing costs for some utilities, making it more difficult and expensive to finance lines, which ultimately drives up electricity rates.
Proposed Framework for Strategic Transmission Siting
Element #1 - Identification and designation of strategic transmission priorities
Key gaps/needs:
Prioritization of transmission projects.
Principles and criteria to identify strategic transmission priorities.
Enabling actions:
Establish dedicated state resource – within an existing agency or through creation of a new transmission entity – to identify state priorities.
Recognize WestTEC 10- and 20- year projects as state priorities and engage with utilities, large loads, and neighboring states to identify paths forward.
Element #2 - Streamlined siting and permitting
Key gaps/needs:
Expedite siting and permitting for priority projects to increase pace of development through assistance in navigating existing permitting frameworks.
Streamline siting and permitting to increase efficiency across all projects, while maintaining existing protections and sufficient opportunity for public comment.
Strengthen public engagement, starting early in the process.
Enabling actions for priority projects:
Projects identified as a priority are deemed to meet the need standard in the Energy Facility Siting Council’s process.
Establish dedicated state liaisons to accompany priority projects from start to finish and provide support through planning and permitting processes.
For priority projects, provide clear direction from the Governor’s Office and agency directors to focus on permitting these projects.
Extend EFSC’s jurisdiction to projects deemed priority projects to ensure consistency, focus state resources, and expedite permitting.
Enabling actions for all projects:
Increase qualified staff at agencies to meet increased demand for permits.
Fund increased staffing needs, including liaison positions, through developer contributions.
Establish EFSC standards specific to transmission lines.
Update Goal 13, Energy Conservation.
Make adjustments to state permitting processes to reduce redundancy and delays while maintaining sufficient opportunity for public comment. This includes cooperation between EFSC, ODOT, the OPUC, DLCD, other relevant state agencies, local governments, and state and federal processes.
Develop a framework for community benefits to inform projects.
Create an opt-in system for landowners in early outreach, with compensation.
Enable counties to defer transmission siting authority to EFSC.
Expand the “Green Corridor” rule to all counties.
Element #3 - Deploy targeted non-wires solutions at increased pace and scale
Key gap/need (non-wires alternatives):
Deploy targeted non-wires solutions at increased pace and scale, particularly in the very near term.
Enabling actions:
Establish a statewide network for peer learning and technical assistance in deploying non-wires solutions.
Continue to advance mechanisms through OPUC processes for investor-owned utilities to improve existing grid utilization.
Expand funding for energy efficiency and demand side flexibility by removing the cap on the public purpose charge contribution for large loads.
Element #4 - Catalyzing projects through financial support and procurement
Key gaps/needs:
Ensure that priority transmission lines can be built at the pace and scale needed to meet reliability, affordability, and state clean energy goals.
Mitigate ratepayer impacts of transmission development.
Enabling actions:
Address wildfire liability and accountability, building on report expected from the OPUC in fall 2026.
Direct an existing agency or state transmission entity to attract federal funding for transmission projects, including supporting Tribes, utilities, and counties in securing federal funding.
Enable state bonding authority to support low-cost transmission infrastructure development.
Establish the state as a transmission developer-of-last-resort, including the ability to issue competitive tenders to ensure needed transmission is built in a timely manner.